Schedule changes

Task% DoneOldNewChg?Remaining
3.1d System Design 100 3 4 Late 0
3.2 Smell Implementationn 100 16 13 Early 0
3.2b Smell Implementationn 100 10 25 Late 0
3.2c Smell Implementationn 100 35 50 Late 0
3.2d Smell Implementationn 100 12 18 Late 0
2.1 GUI Design 100 10 6 Early 0
2.1b GUI Implementation 100 25 31 Late 0
2.2 User Manual 100 13 15 Late 0
4.1 Colour refinement 100 8 20 Late 0
4.1b Colour refinement100 25 25    
4.1c Colour refinement 100 20 44 Late 0
5.1 Reaction Acquisition20 5 5    
7.1 Virtual Toffee100 10 10    
7.1b Virtual toffee100 12 12    
7.2 Set-up code 100 7 4 Early 0
8.2b Documentation 100 5 1 Early 0
8.2c Documentation 100 6 1 Early 0

Summary:

Completed tasks:

     On time: 3 Early: 5 (19 days) Late: 8 (81 days)

Ongoing tasks:

     On time: 1 Early: 0 (0 days) Late: 0 (0 days)

The project is 62 days behind schedule.